The Public, West Bromwich, UK - Custom sound & stage temporary power distribution.

This remarkable and unusual building opened in June 2008 and provides a number of event spaces beneath some unusual architecture. Fagan Electrical won the bidding to carry out the technical installation work and worked closely with Theatre Consultant Paul Covell to install a large number of cleverly design facility panels which blended in with the architecture. These facility panels provided all necessary stage lighting outlets, sound tie lines, technical and clean earth sound power along with data, video and intercom connections. Working alongside Fagan Electrical, Robolights undertook the manufacture and pre-wiring of all facility panels, providing them ready connect straight to the installed wiring. Robolights also manufactured two, bespoke temporary power distribution units each measuring 1.3m in height and incorporating MCB and RCD protected outlets from 13A through to 125A in single and three phase configurations.

Public Web site

Fagan Electrical Web site